Question: A simple CPM network has three activities, D, E, and F. D is an immediate predecessor of E and of F. E is an immediate
A simple CPM network has three activities, D, E, and F. D is an immediate predecessor of E and of F. E is an immediate predecessor of F. The activity durations are D=4, E=3, F=7.
| The critical path is D-E-F, duration 15. | ||
| The critical path is D-F, duration 12. | ||
| Slack at D is 3 periods. | ||
| Slack at E is 3 periods. | ||
| The critical path is D-E-F, duration 14. |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts