Q1-A 100mm diameter stormwater pipe is to be laid at a constant grade from the location of
Question:
Q1-A 100mm diameter stormwater pipe is to be laid at a constant grade from the location of the existing pit at chainage 0m, to the proposed pit at chainage 27.7m ( note that the top of the pipe needs to be 500mm below the surface at chainage 0 and at chainage 27.7m).
a- what is the grade as a percentage? answer to one decimal place and show your calculation
b-Calculate the RL of the INVERT (bottom) of the pipe at chainage 5.0m
c determine the cover (from the TOP of the pipe to the ground surface ) at 5.0m
Q2- what must be the grade of the pipe from chainage 0.0m to 20.0m for the cover at 20.0m to be 500mm? express the grade as a ratio, percentage and angel and show your working. draw the pipe INVERT on longitudinal section
Q3- Continue the pipe from this point at chainage 20.0, (from Q2 ) and determine the slope from here (as a %) to reach the proposed pit at chainage 27.7m such that there is still 500mm of cover to the pipe. Draw this section of pipe on longitudinal section.
Elementary Surveying An Introduction to Geomatics
ISBN: 978-0273751441
13th Edition
Authors: Charles D. Ghilani, Paul R. Wolf