Question: Q2. Calculate, for the following project data, the a) Normal Duration b) Crash Duration (minimum/least project duration) c) Normal and Least Cost Overhead or indirect

Q2. Calculate, for the following project data,
Q2. Calculate, for the following project data, the a) Normal Duration b) Crash Duration (minimum/least project duration) c) Normal and Least Cost Overhead or indirect costs are $100 per day. Activity IPA Cost MA A B D E F Duration (Days) Normal Crash 4 2 8 5 3 2 10 6 8 6 7 4 Normal 400 800 600 500 800 700 Crash 500 980 700 600 950 1000 AB B, C alat