Question: Question 1: Calculate, for the following project data, the a) Normal Duration b) Crash Duration (Minimum project duration) c) Normal and Least Cost Overhead or

Question 1: Calculate, for the following project data, the

a) Normal Duration

b) Crash Duration (Minimum project duration)

c) Normal and Least Cost

Overhead or indirect costs are $120 per day.

Question 1: Calculate, for the following project

\begin{tabular}{|c|c|c|c|c|c|} \hline \multirow{2}{*}{ Activity } & \multirow{2}{*}{ IPA } & \multicolumn{2}{|c|}{ Duration (Days) } & \multicolumn{2}{c|}{ Cost } \\ \cline { 2 - 6 } & & Normal & Crash & Normal & Crash \\ \hline A & & 5 & 4 & 500 & 600 \\ \hline B & A & 7 & 5 & 350 & 500 \\ \hline C & A & 8 & 5 & 800 & 920 \\ \hline D & A & 11 & 7 & 1200 & 1400 \\ \hline E & B, C & 6 & 4 & 600 & 700 \\ \hline F & C & 4 & 4 & 500 & 500 \\ \hline G & D, F & 7 & 5 & 700 & 1000 \\ \hline H & E, F & 6 & 5 & 300 & 420 \\ \hline \end{tabular}

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!