Question: Q2) TASK PREDECESSOR DURATION A ---- 2 B --- 4 C A 3 D A 5 E B 1 F C 3 G C 6

Q2)

TASK PREDECESSOR DURATION
A ---- 2
B --- 4
C A 3
D A 5
E B 1
F C 3
G C 6
H D 3
I E 4
J F 1
K G,H 5
L G, H, I 3
M J, K , L 2

Perform critical path analysis by finding:

  1. Earliest start
  2. Latest start
  3. Earliest finish
  4. Latest finish
  5. Slack
  6. Critical path

Also, draw the Gantt Chart