Question: Q2) TASK PREDECESSOR DURATION A ---- 2 B --- 4 C A 3 D A 5 E B 1 F C 3 G C 6

Q2) TASK PREDECESSOR DURATION A ---- 2 B --- 4 C A 3 D A 5 E B 1 F C 3 G C 6 H D 3 I E 4 J F 1 K G,H 5 L G, H, I 3 M J, K , L 2 Perform critical path analysis by finding: a) Earliest start b) Latest start c) Earliest finish d) Latest finish e) Slack f) Critical path Also, draw the Gantt Chart