Q2. The following table provides the information necessary to construct a project network and project crash data. "Crash" is the maximum number of days you can reduce to. What is the earliest time and cost you can complete project with and without crashing? Use the AON Method. (15 marks) Activity Predecessors Normal Crash Normal Crash 1 20 8 $1000 $1480 2 24 20 1200 1400 3 14 7 700 1190 4 10 6 500 820 5 3 11 5 550 730