Question: Q.2) The process shown below contains several tasks. Tasks A are parallel. Tasks C and D are simultaneous. Task A 20 min/unit Task C 10

Q.2) The process shown below contains several
Q.2) The process shown below contains several tasks. Tasks A are parallel. Tasks C and D are simultaneous. Task A 20 min/unit Task C 10 min/unit Task B 12 min/unit Task E 8 min/unit Task D Task A 20 min/unit 5 min/unit a) What is the throughput time? b) Which task is the bottleneck? c) What is the bottleneck time? d) If the firm operates 10 hours/day, 6 days/week, what is the weekly capacity of this process