Question: Q3. Consider the following project. Draw the project network, determine the time to complete the project and critical path. Complete the following table for activities

Q3. Consider the following project. Draw the

Q3. Consider the following project. Draw the project network, determine the time to complete the project and critical path. Complete the following table for activities E, F and I. Use the AOA method. (6 + 3 + 6 = 15 marks) Activity Predecessors A B A D B E B F B G C,D H E F J GH K Time (weeks) 6 4 2 9 10 12 9 2 |IS ANCO 15 9 Act. Dur. ES LS EF LF TF FF Arc ii E F