Question: Q3: Draw the critical path for the network activities shown below. What is the duration of the critical path. ________. Activity Duration Immediate Predecessors A

Q3: Draw the critical path for the network activities shown below.

What is the duration of the critical path.

________.

Activity Duration Immediate Predecessors

A 4 --

B 2 A

C 7 --

D 4 A

E 5 B,C,D