Question: Question Five : Draw the critical path for the network activities shown below. What is the duration of the critical path. ________. Activity Duration Immediate
Question Five: Draw the critical path for the network activities shown below.
What is the duration of the critical path.
________.
Activity Duration Immediate Predecessors
A 4 --
B 2 A
C 7 --
D 4 A
E 3 B,D
F 4 B,D
G 5 E,F, C
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
