Question: Q4: The network below represents a project being analyzed by the critical path method. Activity durations are A=5,B=2,C=12,D=3,E=5,F=1,G=7,H =2,I=10, and J=6. a. What is the

Q4: The network below represents a project being
Q4: The network below represents a project being analyzed by the critical path method. Activity durations are A=5,B=2,C=12,D=3,E=5,F=1,G=7,H =2,I=10, and J=6. a. What is the duration of path A-B-E-H-J? c. What is the critical path of this network? d. What is the length of the critical path? Q5. Which mission statement of STC, Zain or Mobily you liked the most? Why