Question: Q5. 20pts [Exercise 12.6] This problem studies scheduling anomalies. Consider the task precedence graph below with eight tasks. 1 8 e-5 2 7 e, 10
![Q5. 20pts [Exercise 12.6] This problem studies scheduling anomalies. Consider the](https://dsd5zvtm8ll6.cloudfront.net/si.experts.images/questions/2024/09/66f4535f5de6a_15866f4535ea9ecb.jpg)
Q5. 20pts [Exercise 12.6] This problem studies scheduling anomalies. Consider the task precedence graph below with eight tasks. 1 8 e-5 2 7 e, 10 3 4 e= 5 5 es= 5 6 e = 5 In the figure, ei denotes the execution time of task i. Assume task i has higher priority than task j if i