Question: A production process has two machines. The first machine has a capacity of 500 units per hour and the second machine has a capacity of
A production process has two machines. The first machine has a capacity of 500 units per hour and the second machine has a capacity of 350 units per hour. Demand for the process is 100 units per hour.
(a) In a push process, what would be the utilization of the first machine?
(b) How would the situation change with a pull system?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
