Question: Quality control (hello ,sorry ,i need an answer within 30 to 20 minutes ,please) Q2/ Draw the network diagram for the next project, then rate

Quality control
(hello ,sorry ,i need an answer within 30 to 20 minutes ,please)
Quality control (hello ,sorry ,i need an answer
Q2/ Draw the network diagram for the next project, then rate (u) and (v) that include two or more critical paths for the project. Find the critical project time? Pre. Act. Activity A B C D E F G H I J K L M N A A A A C,D F G B B E E HJ,K I,L,M Duration 13 4 8 4 17 u 13 13 14 6 V 3 8 11