Question: Quantitative Question ( Write legibly; Credit will be given only if appropriate work is done. ) A company needs to manage a project which consists
Quantitative Question (Write legibly; Credit will be given only if appropriate work is done.)
A company needs to manage a project which consists of the following set of activities:
| Activities | Days Required | Predecessor Activities |
| A | 8 | - |
| B | 4 | A |
| C | 5 | A |
| D | 11 | B, C |
| E | 3 | C |
| F | 10 | E |
| G | 7 | D, F |
(a) Draw a CPM network for this problem. BE TIDY. Use the Activity On Node (AON) notation. (3 Points)
(b) Manually determine the earliest and latest start and finish times for each activity and the amount of slack for each activity. (5 Points)
(c) What is the critical path for the project and how long should it take to complete it? (2 Points)