Question: Quantitative Question (Write legibly; Credit will be given only if appropriate work is done.) Consider the following work breakdown structure for a project: Activity Start

Quantitative Question (Write legibly; Credit will

Quantitative Question (Write legibly; Credit will be given only if appropriate work is done.) Consider the following work breakdown structure for a project: Activity Start Node Finish Node Optimistic Time Most Likely Time Pessimistic Time . 1 2 31 40 49 B 1 3 44 50 56 C 2 4 48 60 72 D 3 4 42 31 34 What is the probability that this project will be completed within 120 days