Question: Ques la : Imagine that this project has a project float of 3 months. Which activity or activities presented above would you crash to save

Ques la : Imagine that this project has a project float of 3 months. Which activity or activities presented above would you crash to save three months on the project, assuming that the activities listed above represent critical path activities? Ques 1b: How much would it cost to crash this project Original Crash Original Crash Extra Duration Duration Time Cost Cost Cost Cost per Activity (Months) (Months) Savings (Dollars) (Dollars) (Dollars) Month 14 12 $10,000 $14,000 $4,000 $2,000 9 8 $17,000 $27,000 $10,000 $10,000 $25,000 $26,000 $1,000 $1,000 2 $14,000 $20,000 $6,000 $3,000 $27,000 $36,000 $9,000 $3,000