Question: Question 2 [13 Marks Cost per Extra Cost Month Activity Original Crash Time Original Crash Duration Duration Savings Cost in Cost (in (in Dollars Months)

Question 2 [13 Marks Cost per Extra Cost Month Activity Original Crash Time Original Crash Duration Duration Savings Cost in Cost (in (in Dollars Months) Months) F 14 12 2 10.000 14,000 A 9 8 17,000 27,000 H 3 2 1 25,000 26,000 G 7 5 2 10,000 16,000 11 8 3 27,000 36,000 4,000 10,000 1,000 6,000 9,000 2.000 10,000 1,000 3,000 3,000 1. Imagine that this project has a project float of -3 (minus three) months. Which activity or activities presented above would you crash to save three months on the project, assuming that the activities listed above represent critical path activities? 2. How much would it cost to crash this project