On a construction project there are 2 types of acceleration, actual and constructive. Actual acceleration occurs when the Owner directs the GC to complete the project ahead of the date contained in the Baseline or accepted schedule." Constructive acceleration occurs when the GC is delayed by some Owner/Architect action or inaction
True
False