Question: Question 1 1 . 1 Define the term earthworks: ( 3 ) 1 2 A contractor has excavated a 4 2 0 m long trench

Question 1
1.1 Define the term "earthworks":
(3)
12 A contractor has excavated a 420m long trench with an average woth of 14.5A and longitudinal section as follows:
L=6700E
The following rates of payment are applicable:
Soft material
. Soft material excavation, excavation depth 0 to 0,5m below natural ground level: R60 per m3
Soft material excavation, excavation depth >0,5m to 22,5m below natural ground Aevel: R7Oner m3
Intermediate material
Intermediate excavation, excavation depth 0 to 1.2m below natural ground level: R75 per m3
Intermediste excavation, excavation depth >1.2m to 3.0m below natural ground level: R88 per m3
Hard material
Herd exravation, excavation depth 0 to 1.5m below natural ground level: R110 per m2
Hard excavation, excavation depth exceeding 1.5m below natural ground level: R130 per m3
Calradaie the payment due to the contractor for excavatipn of the trench.
(10)
Question 1 1 . 1 Define the term "earthworks": (

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!