Question: Question 1: 1 6 A 8 B 5 E 3 H 6 D 8 G 2 F Determine each tasks: Early start and early finish
Question 1:
| 1 | 6 |
|
| A | ||
|
|
|
|
|
| 8 |
|
| B | ||
|
|
|
|
|
| 5 |
|
| E | ||
|
|
|
|
|
| 3 |
|
| H | ||
|
|
|
|
|
| 6 |
|
| D | ||
|
|
|
|
|
| 8 |
|
| G | ||
|
|
|
|
|
| 2 |
|
| F | ||
|
|
|
|
- Determine each tasks:
- Early start and early finish dates
- Late start and finish dates
- Calculate the float for each task
- Identify the critical path and the total days for the path
- If activity E changes from 5 days to 10 days, what is the impact on the critical path and total duration of the project?