Question: Question - 1 ( 1 Point ) Highlight only one answer An activity has an early start ( ES ) of day 3 , a
Question Point Highlight only one answer
An activity has an early start ES of day a late start LS of day an early finish EF of day and a late finish of day the activity:
A Has a lag
B Is progressing well
C Is not on the critical path
D Is on the critical path
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
