Question: Question - 1 ( 1 Point ) Highlight only one answer An activity has an early start ( ES ) of day 3 , a

Question-1(1 Point) Highlight only one answer
An activity has an early start (ES) of day 3, a late start (LS) of day 9, an early finish (EF) of day 7, and a late finish of day 13, the activity:
A. Has a lag
B. Is progressing well
C. Is not on the critical path
D. Is on the critical path