Question: Question 1 2 5 pts The probability that the project would be completed within 4 0 days: 0 . 0 2 2 8 0 .

Question 1
25 pts
The probability that the project would be completed within 40 days:
0.0228
0.0456
0.4772
0.9772
None of the above