Question: Question 2. What is the probability that the project will be completed within 100 days? Activity Predecessor optimistic most likely pessimistic A 8 10 14

Question 2. What is the probability that the

Question 2. What is the probability that the project will be completed within 100 days? Activity Predecessor optimistic most likely pessimistic A 8 10 14 B 14 20 26 A,B 16 20 22 A,B 24 30 36 D E E C 28 36 46 F D, E 18.5 20 21.5