Question: QUESTION 1 2 Table 7 . 6 Activity Immediate Predecessor ( s ) Time ( weeks ) A - - 3 B - - 4

QUESTION 12
Table 7.6
Activity Immediate Predecessor(s) Time (weeks)
A --3
B --4
C --2
D A 4
E A, B 5
F A, B, C 2
G D, E 1
H E 6
I E, F 2
J G, H, I 4
K H, I 3
L I 6
Using Table 7.6, what is the latest start time for activity A?
day 1
day 2
day 0
day 3 or later