Question: Question 1 2/2 pts Task 1 Resource 1 100 units/hr Task 2 Resource 2 90 units/hr Task 3 Resource 3 80 units/hr Which resource is

Question 1 2/2 pts Task 1 Resource 1 100 units/hr

Question 1 2/2 pts Task 1 Resource 1 100 units/hr Task 2 Resource 2 90 units/hr Task 3 Resource 3 80 units/hr Which resource is the bottleneck in the process shown above? Task 3 Task 1 Resource 2 Resource 3 Task 2 Resource 1 Question 2 0/3 pts What is the capacity of the process in the previous problem (in units/hr)? Note: answer should include at least 2 digits after the decimal. 10