Question: Question 5 0/4 pts Task 1 Resource 1 100 units/hr Task 2 Resource 1 OR Resource 2 130 units/hr 70 units/hr Task 3 Resource 2

Question 5 0/4 pts Task 1 Resource 1 100 units/hr

Question 5 0/4 pts Task 1 Resource 1 100 units/hr Task 2 Resource 1 OR Resource 2 130 units/hr 70 units/hr Task 3 Resource 2 80 units/hr Task 4 Resource 3 70 units/hr Which resource(s) is (are) the bottleneck(s) in the process shown above? Resource 1 Resource 3 Task 3 Task 4 Task 1 Resource 2 Task 2 Question 6 0/5 pts What is the capacity of the process in the previous question? Note: answer should include at least 2 digits after the decimal. 130