Question: QUESTION 1 ( 3 0 MARKS ) table [ [ table [ [ 1 . 1 As a member of the Vaal River
QUESTION
MARKS
tabletable As a member of the Vaal River City Project Management team, you have been assigned to develop theprocurement management plan for overseeing the R billion worth of supplies required for the project. Identifythe key factors that must be taken into account when drafting the procurement plan. Provide relevant examples tosupport your explanation.table As part of the Vaal River City Interchange project, you are responsible for excavating cubic feet ofsoil which will be repurposed for other construction activities. According to the project management plan, thetarget is to excavate cubic feet of soil per week, at a rate of R per cubic foot. In the first month's progressreport submitted to the resident civil works manager, the project's Earned Value EV was reported as Rwhile the Actual Cost AC was R For the second month's progress report, the Earned Value wasR and the Actual Cost was R By the end of the third month weeks cubic feet ofsoil remains to be excavated, with the total cost incurred to date amounting to R With reference to theinformation provided, determine and comment on the status of the project for each of the following terms.i Earned Value.,ii Planned Value,iii Schedule Variance,iv Cost Performance Index.,v Schedule Performance Index.,
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
