Question: Question 1 3 What does it mean to practice avoidance in responding to a negative risk? To change the project plan to eliminate the threat
Question
What does it mean to practice "avoidance" in responding to a negative risk?
To change the project plan to eliminate the threat
To adopt less complicated processes to reduce the probability of risk
To acknowledge the risk and not take action
To shift the impact of a threat to a third party