Question: Question 1 ( 4 0 points ) : For the geometric and traffic characteristics shown below, each approach was assumed to have one dedicated left

Question 1(40 points):
For the geometric and traffic characteristics shown below, each approach was assumed to have
one dedicated left-turn lane, one through lane, and one through-right lane.
Calculate the signal cycle length and phase lengths for the intersection using the
Webster method. (30 points)
Recalculate the signal cycle length of Question 1 using the HCM method and an
intersection critical vc ratio of 0.85.(10 points)
Assume the following saturation flows:
Through lanes: 1600vehh?ln
Through-right lanes: 1400vehh?ln
Left lanes: 1000vehh?ln
Left-through lanes: 1200vehh?ln
Left-through-right lanes: 1100vehh?ln
Assume the phasing scheme:
Assume yellow time per phase is 3 seconds; the all-read interval is 1 second. The lost time of
each phase is the total of yellow time and all-red time.
Question 1 ( 4 0 points ) : For the geometric and

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!