Question: Question 1 4 ( 1 point ) Saved In crashing a project, a manager will generally focus on activities which: Question 1 4 options: are

Question 14(1 point)
Saved
In crashing a project, a manager will generally focus on activities which:
Question 14 options:
are not on the critical path.
are costly to crash and are on the critical path.
are the least costly to crash.
are on the critical path and are the least costly to crash.