Question: Question 1 4 ( 2 points ) is the rearranging of the project network logic so that critical activities are done in parallel rather than
Question points
is the rearranging of the project network logic so that critical activities are done in parallel rather than sequentially.
Laddering
Fast tracking
Batching
Concurrency
Sequencing