Question: Question 1 4 ( 2 points ) is the rearranging of the project network logic so that critical activities are done in parallel rather than

Question 14(2 points)
is the rearranging of the project network logic so that critical activities are done in parallel rather than sequentially.
Laddering
Fast tracking
Batching
Concurrency
Sequencing