Question: Question 1 4 If you have only two paths through a project network diagram where path 1 has a length of 2 0 weeks and
Question
If you have only two paths through a project network diagram where path has a length of weeks and path has a length of weeks, what is the estimated duration of the project?
There is not enough information to answer.
weeks
weeks
weeks
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
