Question: Question 1 4 If you have only two paths through a project network diagram where path 1 has a length of 2 0 weeks and

Question 14
If you have only two paths through a project network diagram where path 1 has a length of 20 weeks and path 2 has a length of 30 weeks, what is the estimated duration of the project?
There is not enough information to answer.
25 weeks
20 weeks
30 weeks
 Question 14 If you have only two paths through a project

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!