Question: QUESTION 1 A particular project network has two paths through it: Path A and Path B. Path A has an expected completion time of 15

QUESTION 1 A particular project network has two
QUESTION 1 A particular project network has two paths through it: Path A and Path B. Path A has an expected completion time of 15 weeks and a variance in completion time of 8 weeks, while Path B has an expected completion time of 16 weeks and a variance in completion time of 4 weeks. What is the probability that this project is going to take more than 18 weeks? 38 Ob.289 OC 625 d.7246 e. 100%