Question: Question # 1 4 Use the precedence diagram provided for this lab to answer this question. If workstation # 1 is ( I , D

Question #14
Use the precedence diagram provided for this lab to answer this question. If workstation #1 is (I,D)(60 seconds) and workstation #2 is (A,C)(68 seconds) then which of the following would NOT be an acceptable workstation #3?
GB
BEF
BJE
BF
BJ
BJK