Question: Use the precedence diagram provided for this lab to answer this question. If workstation # 1 is ( I , D ) ( 6 0

Use the precedence diagram provided for this lab to answer this question. If workstation #1 is (I, D)(60 seconds) and workstation #2 is (A,C)(68 seconds) then which of the following would NOT be an acceptable workstation #3?
GB
BF
BJE
BJ
BEF
BJK
 Use the precedence diagram provided for this lab to answer this