Question: Question 1 : ( 5 points ) A project to build a new bridge seems to be going very well since the project is well
Question : points
A project to build a new bridge seems to be going very well since the project is well ahead of schedule
and costs seem to be running very low. A major milestone has been reached where the first two
activities have been totally completed and the third activity is complete. The planners were only
expecting to be through the third activity at this time. The first activity involves prepping the site for
the bridge. It was expected that this would cost $ and it was done for only $ The
second activity was the pouring of concrete for the bridge. This was expected to cost $ but
was actually done for $ The third and final activity is the actual construction of the bridge
superstructure. This was expected to cost a total of $ To date they have spent $ on
the superstructure.
Calculate the schedule variance, schedule performance index, and cost index for the project
to date. How is the project going?
Question : point
Schedule the following activities using CPM:
Part a Draw the network points:
Part b What is the critical path? point
Part c How many weeks will it take to complete the project? point
Part d What activities have slack, and how much? point
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock