Question: Question 1: 50/50 Rule Based on the above Gantt chart, the data given below, and by using the 50/50 rule - complete the Earned Value

Question 1: 50/50 Rule Based on the above Gantt

Question 1: 50/50 Rule

Based on the above Gantt chart, the data given below, and by using the 50/50 rule - complete the Earned Value table for tasks A, C, F, J, K M and O.

Planned Value

Actual Costs

Earned Value

Notes. Use the 50/50 rule to determine how much value was earned.

Task A

$3,000

$1,000

Task C

$10,000

$7,000

Task F

$4,000

$2,500

Task J

$6,000

$2,000

Task K

$8,000

$7,000

Task M

$3,000

$3,500

Task O

$3,000

$0

Legend: Planned Task Task has been completed (as of week 3) Tasks whose planned status does not its match actual status Tasks actual status New projected completion

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!