Question: QUESTION 1 7 A simple project listing of five activities, their predecessors, and their respective time estimates are presented here: Activity Immediate Predecessor Time in

QUESTION 17
A simple project listing of five activities, their predecessors, and their respective time estimates are presented here: Activity Immediate Predecessor Time in Days
\table[[A,None,2],[B,A,2],[C,A,1],[D,B and C,3],[E,D,1]]
Using the CPM, which activities have slack in this project?
C
D
C and E
A
B