Question: Question 1 7 Two months into a design project, the customer requests a modification to the product. The change is made without notifying the project

Question 17
Two months into a design project, the customer requests a modification to the product. The change
is made without notifying the project manager. During final testing, the results are different than what was planned for. This
scenario can best be described as an example of which of the following?
Poor scope control
Poor adherence to the communications management plan
Poor development of the quality management plan
Poor definition of the test plan
 Question 17 Two months into a design project, the customer requests

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!