Question: Question 1 7 Two months into a design project, the customer requests a modification to the product. The change is made without notifying the project
Question
Two months into a design project, the customer requests a modification to the product. The change
is made without notifying the project manager. During final testing, the results are different than what was planned for. This
scenario can best be described as an example of which of the following?
Poor scope control
Poor adherence to the communications management plan
Poor development of the quality management plan
Poor definition of the test plan