Question: Two months into a design project, the customer requests a modification to the product. The change is made without notifing the project manager Durng final

Two months into a design project, the customer requests a modification to the product. The change is made without notifing the project manager Durng final lesting the was planned for. This scenario can best be described as an example of which of the following?
Poor scope control
Poor adherence to the communications management plan
Poor development of the quality management plan
Poor definition of the test plan
 Two months into a design project, the customer requests a modification