Question: Question 1 9 A project whose critical path has an estimated time of 1 2 0 days with a variance of 1 0 0 has

Question 19
A project whose critical path has an estimated time of 120 days with a variance of 100 has a 20% chance that
the project will be completed before day (rounded to nearest day).
98
220
112
120
You selected this answer. This was the
correct answer.
124