Question: Question 1 9 A project whose critical path has an estimated time of 1 2 0 days with a variance of 1 0 0 has
Question
A project whose critical path has an estimated time of days with a variance of has a chance that
the project will be completed before day rounded to nearest day
You selected this answer. This was the
correct answer.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
