Question: A project whose critical path has an estimated time of 1 4 5 days with a variance of 1 0 0 has a 2 5

A project whose critical path has an estimated time of 145days with a variance of 100 has a 25% chance that theproject will be completed before day (please round off to twodecimal digits)