Question: Question 1 9 Three signal phases will be designed for a signalized intersection. The calculated optimum cycle length is 6 7 seconds. Assume that each

Question 19
Three signal phases will be designed for a signalized intersection. The calculated optimum
cycle length is 67 seconds. Assume that each phase loses 5 seconds. What is the total
effective green time for all the phases?
(Round to the nearest second and fill in the blank with a number only.)