Question: Question 1. A firm is developing a software package for personal computers. Duration (weeks) 3 4 Immediate Predecessors none A 2 Activity Name and Description

Question 1. A firm is developing a software

Question 1. A firm is developing a software package for personal computers. Duration (weeks) 3 4 Immediate Predecessors none A 2 Activity Name and Description A. Perform market survey B. Design graphic icons C. Develop flowchart D. Design screens E. Module 1 coding F. Module 2 coding G. Module 3 coding H. Module 4 coding I. Merge components & test 6 5 3 7 5 8 A B, C E E, F D, G, H Find Critical Path & Project Duration