Question: A firm is developing a software package for personal computers. Duration (weeks) Immediate Predecessors 4 none 4 A 3 A Activity Name and Description A.

A firm is developing a software package for

A firm is developing a software package for personal computers. Duration (weeks) Immediate Predecessors 4 none 4 A 3 A Activity Name and Description A. Perform market survey B. Design graphic icons C. Develop flowchart D. Design screens E. Module 1 coding F. Module 2 coding G. Module 3 coding H. Module 4 coding I. Merge components & test 6 B, C 5 3 E 9 5 10 E, F D, G, H For the given project, use CPM and find the slack of activity D? 6 07 O None of the above 4 O 5