Question: QUESTION 1 A simple CPM network has five activities, A , B , C , D , and E . A is an immediate predecessor
QUESTION
A simple CPM network has five activities, A B C D and E A is an immediate predecessor of B and of C B is an immediate predecessor of D and of E C is an immediate predecessor of Which of the following statements is TRUE?
A There are five paths in this network.
B There are two paths in this network.
C There are six paths in this network.
D There are three paths in this network.
E There are four paths in this network.