Question: Question 1: Case Study Topic: Timed Management (15 marks) Refer table 1. Activity Network Diagram to answer the questions. Table 1. Activity Network Diagram Activity

Question 1: Case Study Topic: Timed Management (15 marks)

Refer table 1. Activity Network Diagram to answer the questions.

Table 1. Activity Network Diagram

Activity

Description

Estimated Duration

Predecessor

A

Evaluate current technology platform

2

None

B

Define user requirements

5

A

C

Design page layouts

4

B

D

Set-up server

3

B

E

Estimate Web traffic

1

B

F

Test web pages and links

4

C,D

G

Move web pages to production environment

3

D,E

H

Write announcement for newsletter

2

F,G

I

Train users

5

G

J

Write report to top management

1

H,I

  1. From the table, draw a network diagram.

(5 marks)

  1. Cabulate possible path for the project.

(5 marks)

  1. Identify the critical path for the project and give reason for your answer.

(2 marks)

  1. Discuss THREE (3) reasons why critical path is beneficial for the Project Manager?

(3 marks)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!