Question: Question 1: Case Study Topic: Timed Management (15 marks) Refer table 1. Activity Network Diagram to answer the questions. Table 1. Activity Network Diagram Activity
Question 1: Case Study Topic: Timed Management (15 marks)
Refer table 1. Activity Network Diagram to answer the questions.
Table 1. Activity Network Diagram
| Activity | Description | Estimated Duration | Predecessor |
| A | Evaluate current technology platform | 2 | None |
| B | Define user requirements | 5 | A |
| C | Design page layouts | 4 | B |
| D | Set-up server | 3 | B |
| E | Estimate Web traffic | 1 | B |
| F | Test web pages and links | 4 | C,D |
| G | Move web pages to production environment | 3 | D,E |
| H | Write announcement for newsletter | 2 | F,G |
| I | Train users | 5 | G |
| J | Write report to top management | 1 | H,I |
- From the table, draw a network diagram.
(5 marks)
- Cabulate possible path for the project.
(5 marks)
- Identify the critical path for the project and give reason for your answer.
(2 marks)
- Discuss THREE (3) reasons why critical path is beneficial for the Project Manager?
(3 marks)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts