Question: Question [ 1 ] : Develop the AON network diagrams for the project. Calculate ES and EF using Forward Pass calculations. Calculate LS and LF
Question :
Develop the AON network diagrams for the project.
Calculate ES and EF using Forward Pass calculations.
Calculate LS and LF using Backward Pass calculations.
Construct a table to show the activity slack time and activity type critical or noncritical
Draw Gantt chart of the ES schedule.
Show the activity slack in the Gantt chart.
What is the project completion time?
What are the critical path activities?
What are the slack times of activities E and J
How many paths are there in the project network?
Identify all burst activities and merge activities.
tableActivitytableImmediatePredecessor ActivitytableTimeWeeksABCADBEC DFEGEHF GIH I,JI,KI,LJ K LM
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock